A short guide
Does the law require a method statement?
For most construction work, no. It is worth saying plainly, because almost every page offering you a method statement template implies otherwise. HSE describes a method statement as a document that “describes in a logical sequence exactly how a job is to be carried out”, and says that while they are “not required by law”, they are prepared for many construction activities anyway, as a practical way to plan, manage and monitor the work.
There is one case HSE singles out. For demolition, dismantling or structural alteration, HSE says the arrangements for carrying out the work must be recorded in writing before the work begins, and that this is usually done by means of a method statement. HSE cites no regulation number for it and neither do we.
Source: HSE, Construction: administration and paperwork, checked on gov.uk on 27 November 2026.
What the law does require
Three duties are real, and none of them is a method statement.
- A risk assessment. Every employer must make a suitable and sufficient assessment of the risks to their employees and to others, under regulation 3(1) of the Management of Health and Safety at Work Regulations 1999. A self-employed person must do the same where the work is of a prescribed description, and “any work which is carried out on a construction site” is on that list.
- Recording the significant findings, once you employ five or more people. Regulation 3(6) applies where “the employer employs five or more employees”, and asks for the significant findings of the assessment and any group of employees found to be especially at risk. Below that number the assessment is still required; writing it down is not.
- A construction phase plan, on a CDM project. Where there is more than one contractor, the principal contractor draws one up before the site is set up, and it must set out the health and safety arrangements and the site rules. Where there is only one contractor, that contractor draws it up as soon as is practicable before setting up the site, and the client must make sure it happens.
Source: MHSWR 1999, regulation 3, checked on gov.uk on 27 November 2026.
Source: Prescribed Undertakings Regulations 2015, Schedule, checked on gov.uk on 27 November 2026.
Source: CDM 2015, regulation 12, checked on gov.uk on 27 November 2026.
Source: CDM 2015, regulation 15, checked on gov.uk on 27 November 2026.
A construction phase plan is not a method statement
They get muddled constantly, and they are different documents with different authority behind them. A construction phase plan is a CDM 2015 document covering a whole project: the arrangements and the site rules, drawn up by the principal contractor or, on a single-contractor job, by the contractor. A method statement describes how one job is to be done. A plan often refers to method statements. It is not one of them, and a method statement does not discharge the duty to have one.
And “RAMS” is the trade's word, not the law's
RAMS means a risk assessment and method statement supplied together, usually because a client or a principal contractor asked for them before letting you on site. That request is real and worth answering well. The term itself appears on no official source we could find: the risk assessment is the half with a regulation behind it.
What goes in a method statement
No regulation sets out what one must contain. HSE describes the shape of a useful one, and what this tool asks for follows that description: the scope of the work, the sequence of operations in the order they happen, which risk assessment it follows, the control measures that came out of it, who is responsible and what they are competent to do, the plant and equipment and how you know it is fit to use, access and exclusion, the protective equipment, and the first aid, fire and emergency arrangements. Leave a heading empty and it does not print: a sheet of empty headings reads as a job where nothing was considered, and somebody would sign it.
Why this tool suggests nothing
Other templates arrive pre-filled with hazards and controls. We will not do that, and the reason is HSE's own: “Do not just copy an example and put your company name to it as that would not satisfy the law and would not protect your employees.” A control measure that did not come out of looking at this job, on this site, with these people, is decoration. So the headings are the offer. What goes under them is yours, and it should come off the risk assessment you actually did.
Source: HSE, Risk assessment template and examples, checked on gov.uk on 27 November 2026.
Revisions, and why the number matters
A method statement is revised far more often than it is written from new: the job changes, the client comes back, somebody reads it properly. Every version carries its reference and its revision at the top of the sheet, so the copy in the van can be told from the copy in the site file. Pressing Revise this one instead keeps every word, moves the revision on by one and dates it today.
Who uses one
Trades asked for RAMS before they are let on site: roofers, electricians, scaffolders, groundworkers, fit-out contractors. Principal contractors collecting them from subcontractors. One-person trades who need a document that stands up without pretending to be a safety consultancy. The paper is the same in every case; only the words under the headings change.
The paperwork either side of it
A method statement says how the work will be done. The works order template instructs it and gets it signed off when it is finished, and the quote generator prices it beforehand. None of them carries any of the others' information: they are separate pieces of paper on purpose.
This is not legal or safety advice
Everything above is quoted from HSE guidance and from the regulations themselves, with a link to each source and the date we last read it. It is not advice about your job, and we are not a safety consultancy. Where the work is high risk or you are unsure which duties reach you, read the definitions in CDM 2015 and take proper advice.